'How to set Start Date for Auto-Schedule in JIRA Advanced Roadmaps?
When I use Auto-Schedule in JIRA Advanced Roadmaps for
- an Epic with four stories where some stories some have subtasks
- where every subtask has estimated hours
- no sprint is assigned to the Epic, Stories or Sub-Tasks
- where the Epic is assigned a Start Date of 6/1/2022 (in the Roadmaps field configured for "Start Date")
The proposed schedule generated doesn't begin on 6/1/2022. Instead the next business day is used. In this example it starts on 4/26/2022.
How do you tell Auto-schedule to start on a specific date?
Solution 1:[1]
The only way I know of setting a start date will affect all epics:
- Go into your advanced roadmap
- Click on the three dots right from your roadmap name
- Click on "Configure"
- By default the "Scheduling" settings should open
There you can set the start date.
When you are looking to provide a start date for an Epic/Issue, then this is not possible at the moment: https://jira.atlassian.com/browse/JSWCLOUD-22406?actionOrder=desc
Sources
This article follows the attribution requirements of Stack Overflow and is licensed under CC BY-SA 3.0.
Source: Stack Overflow
Solution | Source |
---|---|
Solution 1 | dewey |